External Market Conditions that Affect Cost of Tendering in Public Institutions: Evidence from Ghana
Augustine Kwasi Amoateng, Kwaku Tuah Osei
Journal of Economics, Management and Trade · pp. 1–12 · Published 18 May 2017
10.9734/BJEMT/2017/33536Abstract
The study examined the external factors or low visibility factors that affect the accuracy of pre-tender estimate among building contractors of public institutions in the Brong and Ashanti Regions of Ghana. The study was structured within the framework of descriptive research approach. The study was conducted between August, 2016 and March, 2017. Building contractors who had registered with the various public institutions within the Ashanti and Brong Ahafo Regions of Ghana constituted the population of the study. The public institutions randomly selected for the study included: Tertiary Institutions, District, Municipal and Metropolitan Assemblies, Hospitals and other Ministries, Departments and Agencies (MDAs). Twenty (20) public institutions and sixty (60) registered construction firms were randomly chosen for the study. Self-administered questionnaire was used to obtain data from the respondents. The study found that the five most important factors that affect the accuracy of cost of tendering are: Material (prices, availability, supply, quality etc.); Currency exchange fluctuations, prevailing economy conditions, labour cost and availability and cost, availbility and supply of equipment. The study thus concludes that external factors affect the accuracy of tender estimates among construction firms. It is recommended that the performance of estimate staff in terms of accuracy should be monitored and a qualified technical staff should be hired in order to obtain an accurate estimate. Further, training, seminars, and workshops must be organised for the construction firms and should aim to improve the local practice in cost estimation and increase the capabilities of estimators in using estimating software packages.
Cited by 1
Richard Oduro Asamoah, Bernard Kofi Baiden, Gabriel Nani · Advances in Civil Engineering · 2019
Related research
- Knowledge of Hospital Staff on the Procedures and Obstacles to Public Procurement in Ghana — shares topic coverage
- Adaptability of COVID-19 Safety Guidelines in Building Construction Sites in Anambra State, Nigeria — shares topic coverage
- A Study into the Supervision Styles Used by Building Contractors for Improving Craftsmen Performance in Anambra State, Nigeria — shares topic coverage
- Financial Performance and the Management Issues of Bumiputera Construction Firms in the Malaysian Construction Industry — shares topic coverage
- Corruption Menace in Building Construction Industry in Nigeria: Causes and Remedies — shares topic coverage
Article metrics
Real usage data collected on this platform.
0
Page views
0
PDF downloads
0
Outbound clicks
1
Citations
Views by country
Approximate, from request IP at view time — not citizenship or institution. Countries with fewer than 5 views are grouped as "Other".
No views recorded yet.
Traffic sources
Referring site, by host.
No traffic recorded yet.
Views and downloads exclude known bots/crawlers. Citations combines this platform's own DOI-resolved index with each external source's own reported total — see Cited by above for individually listed citing works. Last refreshed 0 seconds ago.